Rio 2016 Apps

Enhance your Games experience.

Download
Who are you cheering on?

Who are you cheering on?

Choose your favorite athletes, teams, sports and countries by clicking on the buttons next to their names

Note: Your favourites settings are stored on your computer through Cookies If you want to keep them, refrain from clearing your browser history

Please set your preferences

Please check your preferences. You can change them at any time

Expand Content

This time zone applies to all schedule times

Expand Content
Contrast
Original colours Original colours High contrast High contrast
View all acessibility resources
A new world

Rio 2016 Games venues taking shape as work on Barra Olympic Park progresses

By Rio 2016

Carioca Arenas and Olympic Tennis Centre are among the most developed, with spectator and competition areas already visible

Rio 2016 Games venues taking shape as work on Barra Olympic Park progresses

Carioca Arenas 1, 2 and 3 will host eight sports at the Rio 2016 Olympic and Paralympic Games (EOM/Renato Sette Camara)

Barra Olympic Park, which will be the heart of the Rio 2016 Olympic and Paralympic Games, is continuing to take shape. As building work progresses, the first spectator stands and competition areas are already visible, providing glimpses of what it will be like when the world’s best athletes battle for medals there in less than two years’ time.

“Significant progress has been made and we are happy to see that work is proceeding as planned, and in some cases, is ahead of schedule,” said Alexandre Techima, Rio 2016’s Infrastructure Integration Director. “Venue construction has progressed a lot over the past few months and the structures of a number of arenas are already visible, such as the Carioca Arenas and the Olympic Tennis Centre, as well as the International Broadcasting Centre (IBC), Main Press Centre (MPC) and hotel.”

The three adjacent Carioca Arenas have seen the most progress. Competition areas have already been concreted and the initial structures for the spectator stands are in place. During the Games, the three venues (previously known as Olympic Halls 1, 2 and 3) will host four Olympic sports - basketball, judo, fencing and taekwondo - and four Paralympic sports - wheelchair basketball, wheelchair rugby, boccia and judo.

Carioca Arena 3 will host fencing, taekwondo and Paralympic judo (Photo: EOM/Renato Sette Camara)

Work is most advanced on Carioca Arena 3, where the stand structure has been completed and work is underway on fitting the steel support structures for the roof.

“We have been working very hard to ensure that the venues are designed to meet all the requirements for hosting top-level sports competitions and we are very pleased to see the buildings leave the drawing board and become reality. Now it is possible to envision how they will be operated during the Games,” said Josué Moraes, Rio 2016’s sport group manager for taekwondo and judo.

Designs show how Carioca Arenas 1, 2 and 3 will look once completed (Photo: EOM)

The Olympic Tennis Centre is also taking shape. Work on the centre court’s spectator stands, which will hold 10,000 people, is progressing well and the preparatory earthworks for the other courts has been completed, ready for surfacing.

Construction of the Olympic Tennis Centre spectator stands is progressing well (Photo: EOM/Renato Sette Camara)

The foundations of the Future Arena, the temporary venue that will host the handball and goalball competitions, are nearing completion. Work on the arena’s steel structure is already under way, with the pillars and beams being installed. One of Rio 2016’s main social legacies, the arena will be dismantled after the Games and its parts will be used to construct four public schools in Rio de Janeiro.

The Future Arena’s steel columns and beams are being mounted (Photo: EOM/Renato Sette Camara)

Rio Olympic Arena and Maria Lenk Aquatics Centre, which have been operational since 2007, are scheduled to undergo modifications in the first quarter of 2015. Meanwhile, foundations are being laid for the Rio Olympic Velodrome and Olympic Aquatics Stadium.

While Barra Olympic Park’s nine competition venues will host 24 sports, the site will also be home to two important venues for ensuring that fans all over the world can enjoy the Games: the International Broadcasting Centre (IBC) and Main Press Centre (MPC). Work on the steel frame and concrete levels of the IBC are in the final stages. The foundations of the MPC have been completed and structural work is pressing forward on the basement, ground floor and mezzanine.

With a total surface area of 62,000m2, the 12 IBC studios are beginning to take shape (Photo: EOM/Renato Sette Camara)

Work on the general infrastructure inside the Olympic Park is also progressing well. More than 10.5km of drainage, 5.3km of sewage system, 8.3km of water supply lines, 5km of fire prevention lines, 5km of lighting, 9.9km of medium-voltage grid and 21.9km of telecommunications lines have been installed.

The Barra Olympic Park works are being coordinated by the Rio Municipal Government.

The time-lapse video below shows how the work is transforming the former Rio racing car track into the Barra Olympic Park site: