Rio 2016 Apps

Enhance your Games experience.

Download
Who are you cheering on?

Who are you cheering on?

Choose your favorite athletes, teams, sports and countries by clicking on the buttons next to their names

Note: Your favourites settings are stored on your computer through Cookies If you want to keep them, refrain from clearing your browser history

Please set your preferences

Please check your preferences. You can change them at any time

Expand Content

This time zone applies to all schedule times

Expand Content
Contrast
Original colours Original colours High contrast High contrast
View all acessibility resources
A new world

First tracks laid on new metro line that will link Rio 2016 Olympic Park with rest of city

By Rio 2016

Largest tunnel of its kind in the world will form part of important legacy for city that has been accelerated by the Games

First tracks laid on new metro line that will link Rio 2016 Olympic Park with rest of city

The tunnel between São Conrado and Barra da Tijuca will have 1,100 sections of track, each 18 metres long (Marcelo Horn)

The construction of Line 4 of Rio's metro service, a crucial project for the 2016 Games and the city's residents, has reached an important milestone with the installation of 400 metres of track in the first tunnel to be completed.

The new line, scheduled to start operating in 2016, will link Barra da Tijuca - the large neighbourhood in the west of Rio that will host the Olympic Park - with Ipanema in the south zone, providing easy connections onwards to Copacabana, the city centre and north zone.

The tracks have been laid in the tunel that links Barra with São Conrado - it is the largest tunnel in the world that has been dug through rock between two metro stations. Another 300 metres of track will be laid every week. More than 1,100 sections of track - each 18 metres long and weighing more than a tonne - will be used to complete the tracks, in both directions, in the Barra-São Conrado tunnel.

“The Line 4 project employs nearly 8,000 workers and when finished it will serve 300,000 passengers per day,” said Rodrigo Vieira, from the state government's special projects department.

Line 4, which will have a total length of 16km, is one of the transport projects that has been accelerated because of the Rio 2016 Olympic and Paralympic Games. It is estimated that the new line will result in about 2,000 fewer vehicles per hour on the road during peak times.
 
There will be six new stations - Jardim Oceânico, São Conrado, Gávea, Antero de Quental, Jardim de Alah and Nossa Senhora da Paz - that will integrate with the existing metro Lines 1 and 2. It will be possible to travel from Barra to Ipanema in 15 minutes and from Barra to the city centre in 34 minutes.